Partial power outage in the Klinck, June 14-15, 18:30 – 8:30

ITServices contracted workforces and Plant Operations will be performing a shutdown of one of two Klinck Building power substations from 6:30pm, Saturday, June 14 through 8:30am, Sunday, June 15. This is critical path schedule work required for the IT project installing a new backup motor generator for Klinck IT systems. During this outage there will be a loss of building lights, some power receptacles and most building mechanical systems. As well there will be a loss of power to certain IT Data Centre Hardware Hosted Client server clusters. Old fire hall and Math Annex building will also lose power.